Vendor has informed PM that a critical piece of equipment is backordered. Equipment must be received by April 1 5 , 2 0 0 4
Vendor has informed PM that a critical piece of equipment is backordered. Equipment must be received by April
or project end date will slip.
Feb Issue is identified. Need to meet with vendor to discuss alternatives.
Feb Met with vendor. Vendor thinks they may be able to get part from another warehouse.
March Contacted vendor, who said all warehouses have been checked, and the equipment is not available. The vendor indicated that equipment may be available from another source a business partner Will get back to PM in
week.
March Vendor did not get back as promised, and PM had to call. Vendor indicated that alternate
source did not respond. The vendor will contact the alternate source and respond in "a couple of days.
Question:
The PM usually manages this, and updates based on input from the project team. It is end of day on March
and you are the PM You have not heard back from the vendor. What do you do
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started