Question

1 Approved Answer

Vendor has informed PM that a critical piece of equipment is backordered. Equipment must be received by April 1 5 , 2 0 0 4

Vendor has informed PM that a critical piece of equipment is backordered. Equipment must be received by April 15,
2004 or project end date will slip.
Feb 1- Issue is identified. Need to meet with vendor to discuss alternatives.
Feb 20- Met with vendor. Vendor thinks they may be able to get part from another warehouse.
March 10- Contacted vendor, who said all warehouses have been checked, and the equipment is not available. The vendor indicated that equipment may be available from another source (a business partner). Will get back to PM in 1
week.
March 20- Vendor did not get back as promised, and PM had to call. Vendor indicated that alternate
source did not respond. The vendor will contact the alternate source and respond in "a couple of days.
Question:
The PM usually manages this, and updates based on input from the project team. It is end of day on March 22,
2004, and you are the PM. You have not heard back from the vendor. What do you do?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Ecological Forest Management

Authors: Jerry F. Franklin, K. Norman Johnson, Debora L. Johnson

1st Edition

1478633506, 978-1478633501

More Books

Students also viewed these General Management questions

Question

Define an attribute, and give an example.

Answered: 1 week ago