Ventaz Corp manufactures small windows for back yard sheds. Historically, its demand has ranged from 30 to 50 windows per day with an average of
Ventaz Corp manufactures small windows for back yard sheds. Historically, its demand has ranged from 30 to 50 windows per day with an average of 47 . Alex is one of the production workers and he works eight hours a day, five days a week. Each order is one window and each window takes 10 minutes. What is the cycle time for an order? A. 100 minutes per window B. 10 minutes per window C. 500 minutes per window D. 245 minutes per window