Ventaz Corp manufactures small windows for back yard sheds. Historically, its demand has ranged from 30 to 50 windows per day with an average of
Ventaz Corp manufactures small windows for back yard sheds. Historically, its demand has ranged from 30 to 50 windows per day with an average of 42. Alex is the one production worker and he works eight hours a day, five days a week. Each order is one window and each window takes 11 minutes. What is the average waiting time in minutes?