Vertis Corporation is interested in cutting the amount of time between when a customer places an order and when the order is completed. Details for
Vertis Corporation is interested in cutting the amount of time between when a customer places an order and when the order is completed. Details for the first quarter of the year are provided here. Choose the correct answer from the options provided. Wait time Inspection time Process time Move time Queue time Days 14 0.6 5 0.4 Knowledge Check 01 What is the throughput time? 26 days 6 days 12 days O 5 days