VMOH Variance Wendys expects to use $1,000,000 in VMOH this year. They use direct labor hours as a cost allocation base. Wendys expects to employ
VMOH Variance Wendys expects to use $1,000,000 in VMOH this year. They use direct labor hours as a cost allocation base. Wendys expects to employ 10 people working 40 hours/week, 52 weeks/year. They end up spending $1,150,000 on VMOH. Workers actually worked 21,000 hours total. Calculate all variances for VMOH.
Step by Step Solution
There are 3 Steps involved in it
Step: 1