Vollmer Manufacturing makes three components for sale to refrigeration companies. The components are processed on two machines: a shaper and a grinder. The times (in
Vollmer Manufacturing makes three components for sale to refrigeration companies. The components are processed on two machines: a shaper and a grinder. The times (in minutes) required on each machine are as follows:
Machine | ||
---|---|---|
Component | Shaper | Grinder |
1 | 6 | 4 |
2 | 4 | 5 |
3 | 4 | 2 |
The shaper is available for 120 hours, and the grinder is available for 110 hours. No more than 200 units of component 3 can be sold, but up to 900 units of each of the other components can be sold. In fact, the company already has orders for 600 units of component 1 that must be satisfied. The profit contributions for components 1, 2, and 3 are $8, $6, and $9, respectively.
(a)Formulate and solve for the recommended production quantities.
component 1 =. units
component 2=. units
component 3=. units
(b)What are the objective coefficient ranges for the three components? (If there is no upper or lower limit, enter NO LIMIT. Round your answers to the nearest integer.)
component 1_____ to ______units
component 2_____ to ______ units
component 3______ to ______ units
(c)
What are the right-hand-side ranges? (Use minutes for time. If there is no upper or lower limit, enter NO LIMIT. Round your answers to the nearest integer.)
shaper availability. _____ to ______
grinder availability _______ to ________
max units of component 3 ______ to _____
max units of component 1 ______ to _______
max units of component 2 ______ to _______
existing orders for component 1 ______ to ______
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started