Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Waltner Corporation's management reports that its average delivery cycle time is 31 days, its average throughput time is 11.3 days, its manufacturing cycle efficiency (MCE)

Waltner Corporation's management reports that its average delivery cycle time is 31 days, its average throughput time is 11.3 days, its manufacturing cycle efficiency (MCE) is 0.44, its average move time is 0.5 day, and its average queue time is 5.00 days.

Required:
a. What is the wait time? (Round your answer to 1 decimal place.)

Wait time days

b. What is the process time? (Round your answer to 1 decimal place.)

Process time days

c. What is the inspection time? (Do not round intermediate calculations. Round your final answer to 1 decimal place.)

Inspection time days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions