Question

1 Approved Answer

Wankky Company worked on only two jobs during August. Information on the jobs is given below: Job 01 Job 02 Direct material $80,000 $92,000 Direct

Wankky Company worked on only two jobs during August. Information on the jobs is given below:

Job 01

Job 02

Direct material

$80,000

$92,000

Direct labour

287,000

219,000

Direct manufacturing labour-hours (DMLH)

21,000

13,300

At the beginning of the year, annual manufacturing overhead (MOH) was budgeted at $3,780,000 and Wankky budgeted 35,000 DMLH per month. Job 01 was completed in August.

Required:

  1. Compute the total cost of Job 01. (10 marks)

Job 01

Direct material

80,00

Direct labour

287,000

Manufacturing overhead applied

  1. Calculate per unit cost for Job 01 assuming it has 3,300 units. (3 marks)

  1. Some business use job order costing and others process costing. What is the difference between these two costing systems? What companies use job costing? What companies use process costing? Briefly explain. (12 marks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cost Accounting With Integrated Data Analytics

Authors: Karen Congo Farmer, Amy Fredin

1st Edition

1119731860, 9781119731863

More Books

Students also viewed these Accounting questions