Washington County s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private
Washington Countys Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the boards decision appear below.
Cost of acquiring additional land for runway $
Cost of runway construction
Cost of extending perimeter fence
Cost of runway lights
Annual cost of maintaining new runway
Annual incremental revenue from landing fees
In addition to the preceding data, two other facts are relevant to the decision. First, a longer runway will require a new snowplow, which will cost $ The old snowplow could be sold now for $ The new, larger plow will cost $ more in annual operating costs. Second, the County Board of Representatives believes that the proposed long runway, and the major jet service it will bring to the county, will increase economic activity in the community. The board projects that the increased economic activity will result in $ per year in additional tax revenue for the county.
In analyzing the runway proposal, the board has decided to use a year time horizon. The countys hurdle rate for capital projects is percent.
Use Appendix A for your reference.
In analyzing the runway proposal, the board has decided to use a year time horizon. The countys hurdle rate for capital projects is percent. The County Board of Representatives believes that if the county conducts a promotional effort costing $ per year, the proposed long runway will result in substantially greater economic development than was projected originally. However, the board is uncertain about the actual increase in county tax revenue that will result. the initial cost of the investment in the long runway is
the annual net cost or benefit from the runway is
Required:
Suppose the board builds the long runway and conducts the promotional campaign. What would the increase in the countys annual tax revenue need to be in order for the proposed runways internal rate of return to equal the countys hurdle rate of percent?
Determine the IRR on the proposed long runway?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started