Question

1 Approved Answer

Washington Countys Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft

Washington Countys Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the boards decision appear below.

Cost of acquiring additional land for runway $ 64,500 Cost of runway construction 280,000 Cost of extending perimeter fence 24,535 Cost of runway lights 33,000 Annual cost of maintaining new runway 16,500 Annual incremental revenue from landing fees 27,500

In addition to the preceding data, two other facts are relevant to the decision. First, a longer runway will require a new snowplow, which will cost $120,000. The old snowplow could be sold now for $12,000. The new, larger plow will cost $8,000 more in annual operating costs. Second, the County Board of Representatives believes that the proposed long runway, and the major jet service it will bring to the county, will increase economic activity in the community. The board projects that the increased economic activity will result in $80,000 per year in additional tax revenue for the county. In analyzing the runway proposal, the board has decided to use a 10-year time horizon. The countys hurdle rate for capital projects is 14 percent.

Use Appendix A for your reference. (Use appropriate factor(s) from the tables provided.)

In analyzing the runway proposal, the board has decided to use a 10-year time horizon. The countys hurdle rate for capital projects is 14 percent. The County Board of Representatives believes that if the county conducts a promotional effort costing $28,000 per year, the proposed long runway will result in substantially greater economic development than was projected originally. However, the board is uncertain about the actual increase in county tax revenue that will result.

Required: Suppose the board builds the long runway and conducts the promotional campaign. What would the increase in the countys annual tax revenue need to be in order for the proposed runways internal rate of return to equal the countys hurdle rate of 14 percent? (Round intermediate and final answer to the nearest dollar amount.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Lease Audits The Essential Guide

Authors: Theodore H Hellmuth

1st Edition

0934055041, 978-0934055048

More Books

Students also viewed these Accounting questions

Question

Develop a program for effectively managing diversity. page 303

Answered: 1 week ago

Question

List the common methods used in selecting human resources. page 239

Answered: 1 week ago