Washington County's Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft

Washington County's Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board's decision appear below.

Cost of acquiring additional land for runway$100,000Cost of runway construction325,000Cost of extending perimeter fence30,640Cost of runway lights49,000Annual cost of maintaining new runway24,500Annual incremental revenue from landing fees67,500

In addition to the preceding data, two other facts are relevant to the decision. First, a longer runway will require a new snowplow, which will cost $200,000. The old snowplow could be sold now for $20,000. The new, larger plow will cost $19,000 more in annual operating costs. Second, the County Board of Representatives believes that the proposed long runway, and the major jet service it will bring to the county, will increase economic activity in the community. The board projects that the increased economic activity will result in $136,000 per year in additional tax revenue for the county.

In analyzing the runway proposal, the board has decided to use a 10-year time horizon. The county's hurdle rate for capital projects is 20 percent.

UseAppendix Afor your reference.(Use appropriate factor(s) from the tables provided.)

Problem 16-47 Internal Rate of Return; Sensitivity Analysis (Section 1) (LO 16-1, 16-3)

In analyzing the runway proposal, the board has decided to use a 10-year time horizon. The county's hurdle rate for capital projects is 20 percent. The County Board of Representatives believes that if the county conducts a promotional effort costing $30,000 per year, the proposed long runway will result in substantially greater economic development than was projected originally. However, the board is uncertain about the actual increase in county tax revenue that will result.

Required:

Suppose the board builds the long runway and conducts the promotional campaign. What would the increase in the county's annual tax revenue need to be in order for the proposed runway's internal rate of return to equal the county's hurdle rate of 20 percent?(Round your intermediate calculations and final answer to the nearest whole dollar.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Multicolumn Journal

Authors: Claudia Gilbertson

10th Edition

128552845X, 9781285528458

More Books

Students also viewed these Accounting questions

Question

How can the explanatory variables be checked for collinearity?

Answered: 1 week ago

Question

1. What does this mean for me?

Answered: 1 week ago