Waterway Industriesmanufactures a product with a standard direct labor cost of two hours at $18 per hour. During July, 2800 units were produced using 5900
Waterway Industriesmanufactures a product with a standard direct labor cost of two hours at $18 per hour. During July, 2800 units were produced using 5900 hours at $18.30 per hour. The labor price variance was
$5400 U.
$1770 U.
$7170 U.