Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Waterways Continuing Problem 2 (Part Level Submission) Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service locations this

Waterways Continuing Problem 2 (Part Level Submission)

Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain which will require special-order sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December 2016.

Raw materials were requisitioned from the companys inventory on December 2 for $5,061; on December 8 for $1,059; and on December 14 for $3,459. In each instance, two-thirds (2/3) of these materials were for J57 and the rest for K52.

Six time tickets were turned in for these two projects for a total amount of 18 hours of work. All the workers were paid $16.50 per hour. The time tickets were dated December 3, December 9, and December 15. On each of those days, 6 labor hours were spent on these jobs, two-thirds (2/3) for J57 and the rest for K52.

The predetermined overhead rate is based on machine hours. The expected machine hour use for the year is 2,112 hours, and the anticipated overhead costs are $840,576 for the year. The machines were used by workers on projects K52 and J57 on December 3, 9, and 15. Six machine hours were used for project K52 (2 each day), and 8.5 machine hours were used for project J57 (2.5 the first day and 3 each of the other days). Both of these special orders were completed on December 15, producing 237 sprinkler heads for J57 and 142 sprinkler heads for K52.

Additional job order activities during this period of time included:

Dec. 1 Purchased raw materials from Durbin Supply Company on account for $53,200.
Dec. 2 Issued $40,000 of direct materials from the companys inventory to jobs other than K52 and J57 and $3,000 of indirect materials.
Dec. 12 Paid Waterways factory salaries and wages in the amount of $65,000.
Dec. 13 Paid the factorys water bill of $9,000.
Dec. 18 Transferred $50,000 of costs from other completed jobs to finished goods.
Dec. 21 Paid the factorys electric bill of $12,000 for Waterways factory.
Dec. 31

Made adjusting entries for the factory that included accrued property taxes of $12,000, prepaid insurance of $8,800, and accumulated depreciation on equipment of $16,000.

Set up the job cost sheets for Job No. J57 and Job No. K52. Determine the total cost for each manufacturing special order for these jobs.(Round unit costs to 2 decimal places, e.g. 12.25.)
Job No. J57 Job No. K52
Total Cost $ $
Unit Cost $

$

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Income Tax Fundamentals 2013

Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill

31st Edition

1111972516, 978-1285586618, 1285586611, 978-1285613109, 978-1111972516

Students also viewed these Accounting questions

Question

2. Prevent fights by avoiding crowded work spaces.

Answered: 1 week ago

Question

En un escenaro de elasticidad punto precio =

Answered: 1 week ago