Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service locations this month. Job 157 and Job K52 involve

image text in transcribed
image text in transcribed
image text in transcribed
Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service locations this month. Job 157 and Job K52 involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December. Raw materials were requisitioned from the company's imventory on December 2 for $5,019; on December 8 for $1,062; and on December 14 for $3,471. In each instance, two-thirds (2/3) of these materials were for 157 and the rest for K52. Six time tickets were turned in for these two projects for a total amount of 18 hours of work. All the workurs were paid $15.5 per hour. The time tickets were dated December 3, December 9 , and December 15. On each of those days, 6 labor hours were spent on these jobs, two-thirds (2/3) for 157 and the rest for K52 The predetermined overhead rate is based on machine hours. The expected machine hour use for the vear is 2.121 hours, and the anticipated overhead costs are $839,916 for the year. The machines were used by workers on projects K52 and 157 on December 3.9. and 15. S1x machine hours were used for project K52 (2 each day), and 8.5 machine hours were used for project 157 (2.5 the first day and 3 each of the other days) Both of these special orders were completed on December 15. producing 200 sprinkler heads for 157 and 100 sprinkler heads for K52 Additional job order activities during this period included: Dec. 1 Purchased raw materials from Durbin Supply Company on account for $53,200. Dec. 2 Issued $40,200 of direct materials from the company's inventory to jobs other than K52 and J57 and $3,000 of indirect materials. Dec. 12 Paid Waterways' factory salaries and wages for $64,800. Dec. 13 Paid the factory's water bill of $8,900. Dec. 18 Transferred $49,500 of costs from other completed jobs to finished goods. Dec. 21 Paid the factory's electric bill of $12,000 for Waterways' factory. Dec. 31 Made adjusting entries forth factory that included accrued property taxes of $12,100, prepaid insurance of $8,700, and accumulated depreciation of $16,000. Set up the job cost sheets for Job No. 157 and Job No. KS2. Determine the total cost for each manufacturing special order far these jobs. (Round unit costs to 2 decimol ploces, eg. 12.25.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Environmental Auditing Fundamentals And Techniques

Authors: J. Ladd Greeno

2nd Edition

091509410X, 978-0915094103

More Books

Students also viewed these Accounting questions

Question

Why is it important to write with the audience in mind?

Answered: 1 week ago