Question
Waterways uses time and material pricing when it bids on irrigation projects.Budgeted data for the coming year are as follows. WATERWAYS CORPORATION Budgeted Costs for
Waterways uses time and material pricing when it bids on irrigation projects.Budgeted data for the coming year are as follows.
WATERWAYS CORPORATION
Budgeted Costs for Irrigation ProjectsTime
ChargesMaterial
Loading
ChargesLabor wages (5,700hours)
$238,260Supervisor's salary
$58,000
Clerical and accountant wages
58,1404,000
Irrigation supplies manager
38,000Overhead
55,86018,800Total
$352,260$118,800
Waterways has budgeted for5,700labor hours. It desires a $14profit margin per hour of labor and18% profit on materials. It estimates the total invoice cost ofmaterials in the coming year will be$660,000.
Compute the rate per hour of labor.(Round answer to 2 decimal places, e.g. 52.75.)
Labor rate$per hour
Compute the material loading charge
Material loading charge
Waterways has received a request for a bid to do parkway for the city. The irrigation manager estimates that it will take about a month to complete the project and require 450 hours of labor and $79,000 of materials Compute the total estimated bid for the parkway project. (Round answer to 0 decimal places, e.g. 5,275.)
Total estimated bid for the parkway project $
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started