Question

1 Approved Answer

Watten Construction contracted to build the Sillimans a house for $50,000. When Watten began digging the foundation, it hit bedrock, which was highly unusual in

Watten Construction contracted to build the Sillimans a house for $50,000. When Watten began digging the foundation, it hit bedrock, which was highly unusual in that area. Watten told the Sillimans that he required an extra $5000 to build the house. The Sillimans agreed, but when the house was done, refused to pay Watten any more than the original contract price. If Watten sues the Sillimans for the extra $5000, what is the result? Why?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials of Business Law

Authors: Anthony Liuzzo

10th edition

1259917134, 9781260091823, 1260091821, 1260159493, 978-1259917134

More Books

Students also viewed these Law questions

Question

2. It is the results achieved that are important.

Answered: 1 week ago