Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Watten Construction contracted to build the Sillimans a house for $50,000. When Watten began digging the foundation, it hit bedrock, which was highly unusual in
Watten Construction contracted to build the Sillimans a house for $50,000. When Watten began digging the foundation, it hit bedrock, which was highly unusual in that area. Watten told the Sillimans that he required an extra $5000 to build the house. The Sillimans agreed, but when the house was done, refused to pay Watten any more than the original contract price. If Watten sues the Sillimans for the extra $5000, what is the result? Why? (IRAC) Don't forget the legal rule.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started