Question

1 Approved Answer

WBS Element Planned Value (PV) Earned Value (EV) Actual Cost (AC) 2.01 Airframe 48,000 48,000 50,000 2.02 Engines 22,000 21,000 23,000 2.03 Avionics 80,000 60,000

WBS Element Planned Value (PV) Earned Value (EV) Actual Cost (AC)
2.01 Airframe 48,000 48,000 50,000
2.02 Engines 22,000 21,000 23,000
2.03 Avionics 80,000 60,000 45,000
2.04 Communications 30,000 30,000 30,000
2.05 Tech. Manuals 42,000 42,000 48,000
2.06 Spares 40,000 35,000 42,000
2.07 Training 80,000 80,000 86,000
Project Total 342,000 316,000 324,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Accounting Uk Gaap Volume 1

Authors: Frank Wood, Alan Sangster

1st Edition

0273718762, 9780273718765

More Books

Students also viewed these Accounting questions