Question

1 Approved Answer

We are evaluating a project that costs $2,220,000, has a 8-year life, and has no salvage value. Assume that depreciation is straight-line to zero over

We are evaluating a project that costs $2,220,000, has a 8-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 94,700 units per year. Price per unit is $39.03, variable cost per unit is $24.10, and fixed costs are $869,000 per year. The tax rate is 23 percent, and we require a return of 11 percent on this project.

a. Calculate the base-case operating cash flow and NPV. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)
b. What is the sensitivity of NPV to changes in the sales figure? (Do not round intermediate calculations and round your answer to 3 decimal places, e.g., 32.161.)
c. If there is a 300-unit decrease in projected sales, how much would the NPV change? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)
d. What is the sensitivity of OCF to changes in the variable cost figure? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)
e. If there is a $1 decrease in estimated variable costs, how much would the OCF change? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)image text in transcribed
Base-case operating cash flow Base-case NPV b. NPV sensitivity c. NPV change d. OCF sensitivity e. OCF change

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Handbook Of Quantitative Finance And Risk Management

Authors: Cheng-Few Lee, John Lee

2010th Edition

0387771166, 978-0387771168

More Books

Students also viewed these Finance questions