We are evaluating a project that costs $756,000, has a six-year life, and has no salvage value.
Question:
We are evaluating a project that costs $756,000, has a six-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 67,000 units per year. Price per unit is $60, variable cost per unit is $25, and fixed costs are $665,000 per year. The tax rate is 35 percent, and we require a return of 20 percent on this project. Suppose the projections given for price, quantity, variable costs, and fixed costs are all accurate to within 10 percent.
Calculate the best-case and worst-case NPV figures. (Negative amounts should be indicated by a minus sign. Do not round intermediate calculations and round your final answers to 2 decimal places (e.g., 32.16).)
NPVBest-case
NPV Worst-case