We have a project ( RedBird ) , with these activities in days: Activity A with duration 4 and no precedents. Activity B with duration

We have a project
(
RedBird
)
,
with these activities in days: Activity A with duration
4
and no precedents. Activity B with duration
1
5
and predecessor. A
,
Activity C with duration
1
and predecessor. A
,
Activity D with duration
1
and predecessor B
,
Activity E has duration
9
and predecessors B and C
,
Activity F has duration
2
and predecessor D
,
and Activity G has duration
1
7
and predecessors of E and F
.
From question #
1
,
what is the slack in node EF
?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding Management

Authors: Richard L. Daft, Dorothy Marcic

10th edition

1305887093, 1305502213, 9781305887091, 978-1305502215

More Books

Students also viewed these General Management questions