Weekly demand at the banana stand is 200 banana with a standard deviation of 50. The replenishment lead time is three weeks from the plantation
Weekly demand at the banana stand is 200 banana with a standard deviation of 50. The replenishment lead time is three weeks from the plantation in Ecuador. The banana stand manager order 1000 bananas