Western Manufacturing produces a single product. The original budget for April was based on expected production of 22,000 units; actual production for April was 24,200
Western Manufacturing produces a single product. The original budget for April was based on expected production of 22,000 units; actual production for April was 24,200 units. The original budget and actual costs incurred for the manufacturing department follow:
Original Budget | Actual Costs | ||||
Direct materials | $ | 356,400 | $ | 400,500 | |
Direct labor | 297,000 | 336,500 | |||
Variable overhead | 126,500 | 125,500 | |||
Fixed overhead | 74,500 | 65,000 | |||
Total | $ | 854,400 | $ | 927,500 | |
Required: Prepare an appropriate performance report for the manufacturing department. (Do not round intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance).)
Western Manufacturing produces a single product. The original budget for April was based on expected production of 22,000 units; actual production for April was 24,200 units. The original budget and actual costs incurred for the manufacturing department follow:
Original Budget | Actual Costs | ||||
Direct materials | $ | 356,400 | $ | 400,500 | |
Direct labor | 297,000 | 336,500 | |||
Variable overhead | 126,500 | 125,500 | |||
Fixed overhead | 74,500 | 65,000 | |||
Total | $ | 854,400 | $ | 927,500 | |
Required: Prepare an appropriate performance report for the manufacturing department. (Do not round intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance).)
Item Actual Cost Variance Direct materials $ 400,500 Direct labor Original Budget Flexed Budget (22,000 units) (24,200 units) $ 356,400 297,000 126,500 74,500 $ 854,400 336,500 Variable overhead 125,500 Fixed overhead 65,000 $ 927,500 TotalStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started