Western Wood Products has two production departments: Cutting and Assembly. The company has been using a single predetermined cost driver rate based on plantwide direct
Western Wood Products has two production departments: Cutting and Assembly. The company
has been using a single predetermined cost driver rate based on plantwide direct labour hours.
That is, the plantwide cost driver rate is computed by dividing plantwide support costs by total
plantwide direct labour hours. The estimates for support costs and quantities of cost drivers for
2006 follow:
Cutting Assembly Total__
Manufacturing support cost 25,000 $35,000 $60,000
Direct labour hours 1,000 3,000 4,000
Machine hours 4,000 2,000 6,000
The company received an invitation from NuTech Ltd. to bid on a job Job # 101. This job
would require direct manufacturing costs in the two departments as follows:
Cutting Assembly
Direct material cost $8,000 $1,400
Direct labour cost $250 $800
Direct labour hours 7 35
Machine 50 -
Required
a) Calculate the single plantwide cost driver rate (using direct labour hours for 2006)
b) Determine the total cost to be charged to Job 101, using the single plantwide rate.
c) Calculate the departmental cost driver rates based on direct labour hours for assembly
and machine hours for cutting. (3 marks)
d) Determine the total cost to be charged to Job 101, using the departmental rates.
e) The company has a policy to add a50% markup to estimated job costs to arrive at the bid
price. Determine the bid price for Job 101, using:
i. the plantwide manufacturing support cost driver rate; and
ii. the departmental manufacturing cost driver rates. (4 mark)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started