We've done 50% of the work on a $290K budgeted project. Our project has spent $180K so far. What is the EV? $145K $180K $290K

We've done 50% of the work on a $290K budgeted project. Our project has spent $180K so far. What is the EV?

$145K

$180K

$290K

Not enough information to calculate it