Question

1 Approved Answer

What are pre-negotiation objectives and when are they required? [FAR 15.406-1] What is a PNM? [ FAR 15.406-3] When is price analysis required? [FAR 15.404-1(a)(2)]

What are pre-negotiation objectives and when are they required? [FAR 15.406-1] What is a "PNM"? [ FAR 15.406-3] When is price analysis required? [FAR 15.404-1(a)(2)] & [CON 170] How do you determine price reasonableness? [FAR 15.405(a)] What are some price analysis techniques? [FAR 15.404-1(b)(2)] When is cost analysis required? [ FAR 15.404-1(a)(3)] & [CON 170] What is a cost objective? [FAR 31.3205] & [CON 170] What is a direct cost? [ FAR 2.101, FAR 31.202] & [CON 170] What is an Other Direct Cost (ODC)? [ Not defined in FAR] & [CON 170] What is an indirect cost? [ FAR 2.101, FAR 31.203] & [CON 170] What is the FAR definition of total cost? [FAR 31.201-1(a)], [FAR 31.205-10], [CON 170] What is an unallowable cost? [FAR 31.205] & [CON 170] What are some cost analysis techniques? [FAR 15.404-1(c)(2)]

Step by Step Solution

There are 3 Steps involved in it

Step: 1

Prenegotiation Objectives and Requirements FAR 154061 Prenegotiation objectives are specific goals developed by the contracting officer before entering into price negotiations with a contractorThese o... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles of Finance

Authors: Scott Besley, Eugene F. Brigham

6th edition

9781305178045, 1285429648, 1305178041, 978-1285429649

More Books

Students also viewed these Accounting questions

Question

1. What does dorsal mean, and what is its oppositepg99

Answered: 1 week ago