What are two types of upfront techniques for monitoring a project's schedule and budget? Forward path and annual value analysis Forward path and earned value
What are two types of upfront techniques for monitoring a project's schedule and budget? Forward path and annual value analysis Forward path and earned value analysis Critical path and annual value analysis Critical path and earned value analysis