Answered step by step
Verified Expert Solution
Question
1 Approved Answer
What can we learn about the process flows from Figure 2? Consider the following issues in your response: Is there a bottleneck in the process?
What can we learn about the process flows from Figure 2? Consider the following issues in your response:
- Is there a bottleneck in the process? If so, where is it? Explain.
- How much processing time does each finished product require?
- How many units per hour is the process capable of producing?
- Is there a relationship between the process bottleneck and output per hour? Explain
**Some say step 1 since it takes 4 mins. others are saying step 5 because the tire balance step needed to be added due to the tire supplier providing faulty tires. So I was not sure what answer is correct for question 1. ***For question three some say The process capable of producing = 60 minutes/4 minutes = 15 units per hour and others says The process is capable of producing 3.33 units per hour.
Figure 2: Process Diagram (Time Shown in Minutes : Seconds) Fork assembly Process time 1:45 Tire balancing Process time 3:00 Step 4 Step 5 1 Powder coating Process time 3:00 Wheel assembly Process time 2:15 Step 3 Step 6 Weld clean-up 2:00 Degrease and powder coat prep:30 Handlebar mounting Process time 1:30 Step 2 Step 7 Steel tubing delivered by forklift Cut tubing :30 Welding Setup time (jig) :15 Process time 3:15 Transport to loading queue for JIT JIS delivery Step 1 Step 8 To the OEM: One delivery per hourStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started