What data does the Integrated Program Management Report (IPMR) Format 3 detail? (IMAGE DESCRIPTION: IPMR Format 3 sample shows section 6, Performance Data, which includes
What data does the Integrated Program Management Report (IPMR) Format 3 detail?
(IMAGE DESCRIPTION: IPMR Format 3 sample shows section 6, Performance Data, which includes representative values for the PMB at the beginning and end of the period, authorized baseline changes, management reserve, and the total budget. Representative values for the PMB at the beginning and end of the period, and authorized baseline changes include: BCWS cumulative to date; BCWS for the reporting period; BCWS for a six period forecast; BCWS by quarter; the to complete value; undistributed budget; and total budget.)
IMPR Format 3 is limited to detailing only the current reporting period budgeted cost for work scheduled (BCWS)data
IMPR Format 3 details current budgeted cost for work scheduled (BCWS), cumulative BCWS data for the beginning and end of the current period, but it does not include any forecasted BCWS.
IMPR Format 3 details current budgeted cost for work scheduled (BCWS), cumulative BCWS data for the beginning and end of the current period, and forecasted BCWS for future reporting periods.
IMPR Format 3 details current and cumulative budgeted cost for work scheduled (BCWS)data for the current period, as well as cumulative budgeted cost for work performed (BCWP)for future reporting periods.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started