What do we mean by an activity s late finish date? The latest an activity can finish without delaying the projecty The earliest starting time
What do we mean by an activitys late finish date?
The latest an activity can finish without delaying the projecty
The earliest starting time for a predecessor activity
The latest an activity can finish without delaying the subsequent activity
The pessimistic time from the PERT calculation