What documentation would a project manager use to determine the necessary resources for an activity? a. By reviewing the activity attributes documentation for activity resource
What documentation would a project manager use to determine the necessary resources for an activity?
a. By reviewing the activity attributes documentation for activity resource requirements
b. By searching the Internet project management Web sites for similar projects with similar objectives and resource needs
c. By interviewing the technical SMEs assigned to the project
d. By using past projects as a guide