What does it mean to mitigate in response to a negative risk? a. To adopt less complicated processes to reduce the probability of risk b.

What does it mean to "mitigate" in response to a negative risk?

a. To adopt less complicated processes to reduce the probability of risk

b. To acknowledge the risk and not take action

c. To change the project plan to eliminate the threat

d. To shift the impact of a threat to a third party

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach To Planning Scheduling And Controlling

Authors: Harold Kerzner

13th Edition

1119805376, 978-1119805373

More Books

Students also viewed these General Management questions

Question

=+a) What is the center line for the R chart?

Answered: 1 week ago

Question

Determine Leading or Lagging Power Factor in Python.

Answered: 1 week ago

Question

=+which it operates?

Answered: 1 week ago

Question

=+How should we organize a book to maximize learning and interest

Answered: 1 week ago