Question

1 Approved Answer

What does it mean when earned value is above planned value? Select an answer: More work has been completed than planned, and the task or

What does it mean when earned value is above planned value?

Select an answer:

More work has been completed than planned, and the task or project is ahead of schedule.

More was spent for the work completed than planned, and the project is behind schedule.

Less work has been completed than planned, and the task or project is ahead of schedule.

Less was spent for the work completed than planned, and the project is under budget.

You are using earned value analysis to track your project's progress. In your project, earned value is higher than planned value. That means the project is _____.

Select an answer:

under budget

behind schedule

over budget

ahead of schedule

A risk that has become reality in your project has led to a cost increase. You have already used the funds reserved to handle this risk and have concluded that you need additional funds that the project does not have. Who is the most likely person or group you need to ask for help?

Select an answer:

the project customer

the project stakeholders

your organization's management team

the project sponsor

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Stephen P Robbins, Mary Coulter

11th Edition

9780273752776, 132163845, 273752774, 978-0132163842

More Books

Students also viewed these General Management questions

Question

What is school belonging? How is it impacted?

Answered: 1 week ago