What information does the payback period provide? Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your

What information does the payback period provide?

Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the projects net present value (NPV). You dont know the projects initial cost, but you do know the projects regular, or conventional, payback period is 2.50 years.

Year

Cash Flow

Year 1 $325,000
Year 2 $450,000
Year 3 $450,000
Year 4 $475,000

If the projects weighted average cost of capital (WACC) is 8%, the projects NPV (rounded to the nearest dollar) is:

$393,092

$353,783

$373,437

$412,747

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Take Charge Of Your Money Now Essential Strategies For Winning In Any Financial Climate

Authors: A.J. Monte, Rick Swope

1st Edition

0345517334, 978-0345517333

More Books

Students also viewed these Finance questions

Question

How does selection differ from recruitment ?

Answered: 1 week ago