What is an accurate difference between the Program Evaluation and Review Technique ( PERT ) and critical path method ( CPM ) ? a .
What is an accurate difference between the Program Evaluation and Review Technique PERT and critical path method CPM
a
CPM involves more work than PERT because it requires several duration estimates.
b
PERT uses different duration estimates whereas CPM uses one specific duration estimate.
c
CPM addresses the risk associated with duration estimates whereas PERT does not.
d
Unlike CPM PERT estimates only when there is no risk of uncertainty.