Question

1 Approved Answer

What is an accurate difference between the Program Evaluation and Review Technique ( PERT ) and critical path method ( CPM ) ? a .

What is an accurate difference between the Program Evaluation and Review Technique (PERT) and critical path method (CPM)?
a.
CPM involves more work than PERT because it requires several duration estimates.
b.
PERT uses different duration estimates whereas CPM uses one specific duration estimate.
c.
CPM addresses the risk associated with duration estimates whereas PERT does not.
d.
Unlike CPM, PERT estimates only when there is no risk of uncertainty.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Time Management

Authors: Patrick Forsyth

6th Edition

1398606197, 978-1398606197

More Books

Students also viewed these General Management questions

Question

The company that first used a production line.

Answered: 1 week ago

Question

Prepare a constructive performance appraisal.

Answered: 1 week ago

Question

List the advantages of correct report formatting.

Answered: 1 week ago