Answered step by step
Verified Expert Solution
Question
1 Approved Answer
What is one of the reasons for using three-point estimating for developing a project schedule? Group of answer choices Bottom-up estimating is more accurate than
What is one of the reasons for using three-point estimating for developing a project schedule? Group of answer choices Bottom-up estimating is more accurate than top-down estimating. Statistically, there is a very small probability of completing a project on any given date. Historical and industry metrics tend to be an accurate predictor of project performance. It gives extra weight to the most likely estimate
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started