What is one of the reasons for using three-point estimating for developing a project schedule? Group of answer choices Bottom-up estimating is more accurate than
\What is one of the reasons for using three-point estimating for developing a project schedule? Group of answer choices Bottom-up estimating is more accurate than top-down estimating. Statistically, there is a very small probability of completing a project on any given date. It gives extra weight to the most likely estimate. Historical and industry metrics tend to be an accurate predictor of project performance