Question

1 Approved Answer

What is required to apply the PRINCE2 model to project governance? a) The governance structure must ensure that projects are aligned to the organisations objectives

What is required to apply the PRINCE2 model to project governance?

a) The governance structure must ensure that projects are aligned to the organisations objectives

b) There must be delegated authorities

c) The model must be checked independently to assure effectiveness

d) It must provide a framework for making decisions throughout the stages of the project

e) All of these

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Brand Management Building Measuring And Managing Brand Equity

Authors: Kevin Lane Keller

4th Global Edition

0273779419, 9780273780045

More Books

Students also viewed these General Management questions

Question

How flying airoplane?

Answered: 1 week ago

Question

The feeling of boredom.

Answered: 1 week ago