What is the best explanation for an SPI of 0.80? Multiple choice question. $0.80 has been spent for each $1.00 of work planned to be
What is the best explanation for "an SPI of 0.80"? Multiple choice question. $0.80 has been spent for each $1.00 of work planned to be accomplished. $1.00 of work has been accomplished for each $0.80 of work scheduled to date. $0.80 of work has been accomplished for each $1.00 of work scheduled to date