What is the change in the project duration that resulted when you changed the duration of the
Fantastic news! We've Found the answer you've been seeking!
Question:
What is the change in the project duration that resulted when you changed the duration of the Design Screens task from weeks to weeks?
Why did the project duration change by this amount?
In what way did the critical path change when you changed the duration of the Design Screens task from weeks to weeks?
Why did the critical path change?
Explain why it Isis not possible for the critical path to split into two or more parallel branches. Carefully consider the current network diagram as you compose your response.
Posted Date: