Answered step by step
Verified Expert Solution
Question
1 Approved Answer
What is the duration in weeks of the following projects? Each task is estimated with a 90% probability when you apply Critical Chain. What is
What is the duration in weeks of the following projects? Each task is estimated with a 90% probability when you apply Critical Chain. What is the minimum required buffer? Project 1 task sequence: 6->4->2->2
Project duration:
Minimum required completion buffer
project 2 task sequence: 8W 4W 4W 2WI 8W
Project duration:
Minimum required feeding buffer:
Minimum required completion buffer:
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started