Question

1 Approved Answer

What is the duration in weeks of the following projects? Each task is estimated with a 90% probability when you apply Critical Chain. What is

What is the duration in weeks of the following projects? Each task is estimated with a 90% probability when you apply Critical Chain. What is the minimum required buffer? Project 1 task sequence: 6->4->2->2

Project duration:

Minimum required completion buffer

project 2 task sequence: 8W 4W 4W 2WI 8W

Project duration:

Minimum required feeding buffer:

Minimum required completion buffer:

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Project Management

Authors: Joseph Heagney

5th Edition

0814437362, 978-0814437360

More Books

Students also viewed these General Management questions