What is the duration of a project with the following activity list? Activity Predecessor Duration A - 2 B A 3 C A 2 D
What is the duration of a project with the following activity list? Activity Predecessor Duration A - 2 B A 3 C A 2 D A, B, C 3 E D 4 Group of answer choices 12 9 11 14