What is the earned value of a work package that has aBudget at Completion (BAC) of $10,000, is 25% complete and has cost $5,000? Choices:

What is the earned value of a work package that has aBudget at Completion (BAC) of $10,000, is 25% complete and has cost $5,000?

Choices:

(A) $1,250

(B) 25%

(C) -$5,000

(D) $2,500