What is the meaning of a Schedule Performance Index (SPI) of 0.85? Schedule performance is favorable, indicating more work is being accomplished than planned. Schedule
What is the meaning of a Schedule Performance Index (SPI) of 0.85? |
Schedule performance is favorable, indicating more work is being accomplished than planned. |
Schedule performance is unfavorable, indicating less work is being accomplished than planned. |
There is no way to interpret the SPI without also looking at the Cost Performance Index (CPI). |