What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Activity Normal Time (days)
What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days?
Activity | Normal Time (days) | Crash Time (days) | Normal Cost | Total Cost with Crashing | Immediate Predecessor(s) |
A | 5 | 4 | $800 | $1,100 | |
B | 7 | 5 | $200 | $500 | |
C | 4 | 3 | $600 | $650 | |
D | 6 | 3 | $750 | $1,500 | A |
E | 6 | 4 | $1,200 | $1,650 | C |
By how many days should each activity be crashed to reduce the project completion time by 4 days?
Activity | Each Activity Should be Reduced BY (days) |
A | |
B | |
C | |
D | |
E |
The total cost of crashing the project by 4 days is $ __________.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started