What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Activity Normal Time (days)

What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days?

Activity

Normal Time (days)

Crash Time (days)

Normal Cost

Total Cost with Crashing

Immediate Predecessor(s)

A

5

4

$800

$1,100

B

7

5

$200

$500

C

4

3

$600

$650

D

6

3

$750

$1,500

A

E

6

4

$1,200

$1,650

C

By how many days should each activity be crashed to reduce the project completion time by 4 days?

Activity

Each Activity Should be Reduced BY

(days)

A

B

C

D

E

The total cost of crashing the project by 4 days is $ __________.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Contemporary Logistics

Authors: Paul R. Murphy, Michael Knemeyer

11th edition

132953463, 2900132953466, 978-0132953467

More Books

Students also viewed these General Management questions