What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? ACTIVITY NORMAL TIME (DAYS) CRASH TIME (DAYS) NORMAL COST
What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days?
ACTIVITYNORMAL TIME (DAYS)CRASH TIME (DAYS)NORMAL COSTCRASH COSTIMMEDIATE PREDECESSOR(S)Design (A)86400450-Wiring (B)651,0001,100-Chip install (C)43600700-Software (D)531,0001,300A, BTesting (E)851,1001,625C
Part 2
The minimum cost of crashing the following project at Sawaya Robotics by 4 days is
$enter your response here
(enter your response as a whole
number).