What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? NORMAL CRASH TIME (DAYS) TIME (DAYS) 6 5 8
What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? NORMAL CRASH TIME (DAYS) TIME (DAYS) 6 5 8 6 3 3 5 ACTIVITY Design (A) Wiring (B) Chip install (C) 4 5 8 NORMAL COST 900 300 500 900 1,000 CRASH COST IMMEDIATE PREDECESSOR(S) 1,000 400 600 Software (D) Testing (E) The minimum cost of crashing the following project at Sawaya Robotics by 4 days is $ (enter your response as a whole number) 1,200 1,600 A, B C