Question
What is the net present value of the following two projects if the required rate of return is 9.75%? (Note, the numbers inredare negative) Year
What is the net present value of the following two projects if the required rate of return is 9.75%?
(Note, the numbers inredare negative)
Year
Project A
Cashflows
Project B
Cashflows
Project A
DCF
Project B
DCF
0
-2,500,000
-3,780,000
1
-150,000
-200,000
2
220,000
400,000
3
487,000
800,000
4
825,000
1,300,000
5
1,200,000
1,800,000
6
1,700,000
2,200,000
NPV
a.NPV for Project A is $2,709,434.20, and the NPV for Project B is $4,040,416.59
b.NPV for Project A is $209,434.20, and the NPV for Project B is $260.416.59
c.NPV for Project A is 5 years and the NPV for Project B is 5 years
d.NPV for Project A is $482,782.72, and the NPV for Project B is $624,881.28
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3