What is the NPV of a project that costs $36,000 today and is expected to generate annual cash inflows of $10,000 for the next 7

What is the NPV of a project that costs $36,000 today and is expected to generate annual cash inflows of $10,000 for the next 7 years, followed by a final inflow of $15,000 in year 8. Cost of capital is 7.9%. Round to the nearest dollar.