What is the primary purpose of a milestone in a project schedule? a To identify project risks. b To mark the end of a project.
What is the primary purpose of a milestone in a project schedule?
a
To identify project risks.
b
To mark the end of a project.
c
To allocate resources to a task.
d
To indicate the completion of a significant project phase or deliverable.